The 2002 Review of Florida's Twenty-Five Long Range Transportation Plans
Prepared for:
The Florida Department of Transportation
Prepared by:
Jeff Kramer, AICP
Edward A. Mierzejewski, Ph.D., P.E.
Center for Urban Transportation Research
College of Engineering
University of South Florida
Tampa, Florida 33620-5375
August 2002
EXECUTIVE SUMMARY
Federal and state transportation laws require that a long range transportation
plan (LRTP) be developed in urban areas of greater than 50,000 people. The
agency responsible for conducting the long range transportation planning
process is the Metropolitan Planning Organization (MPO). The Florida
Metropolitan Planning Organization Advisory Council (MPOAC) assists
individual MPOs in carrying out the urbanized area transportation planning
process by serving as the principal forum for collective policy discussion. In
1997, the MPOAC asked the Center for Urban Transportation Research
(CUTR) at the University of South Florida to conduct a review the LRTPs of
the state's twenty-five MPOs to gain a comprehensive understanding of the
issues and concerns facing Florida's MPOs and the manner in which those
issues and concerns were being assessed and documented in the long range
transportation planning process. The study made several suggestions for
improving the regional transportation planning process and documenting that
process in the long range transportation plans, both in terms of technical
approach and structure.
In 2000, CUTR was asked to conduct a comparative review of the updated long
range transportation plans produced by the Florida MPOs located in clean air
non-attainment areas. In general, that review identified a number of
improvements in various areas compared to the 1997 LRTPs. However, many
of the same issues and challenges identified in the 1997 study were still
apparent.
In 2002, CUTR was asked to revaluate twenty-five MPO long range
transportation plans. Each MPO had completed at least one update cycle since
the initial review in 1997. Additionally, federal transportation legislation added
a few new emphasis areas for LRTPs and provided slightly different guidance to
direct the long range transportation planning process. CUTR was directed to
pay particular attention to the methods used to establish project priorities,
identify needs and move projects from needs plans to cost feasible plans.
In general, the quality of the most recent long range transportation plans
improved significantly compared to those reviewed in 1997 or 2000. Overall,
plan documents were more user-friendly and concise. They also contained less
jargon and richer descriptions of issues and challenges. There appeared to be a
somewhat more balanced reliance on modeling and a more obvious assessment
of a wider range of planning considerations than roadway level-of-service
deficiency. There were numerous examples of innovative public involvement
efforts and improved regional and interagency coordination. There was an
increase in the consideration of potential social and community impacts in the
decision-making process and thoughtful inclusion of community concerns into
the decision-making process.
A variety of methods were used to select projects for the cost feasible plan with
the most popular approach being the use of a weighted prioritization formula.
Almost all the MPO plans incorporated the concepts of multimodalism and
intermodalism, including such alternative strategies as intelligent transportation
systems (ITS), corridor management, and transportation demand management
(TDM). Even so, financial shortfalls between the costs of identified needs and
reasonably available revenues remained a significant and widespread
phenomenon. When added together, the statewide 20-year shortfall estimate is
$37.7 billion (in year 2000 dollars) -- a 43% increase over the 1997 statewide
shortfall estimate.
Although the 2002 review identified numerous improvements in long range
transportation planning around the state, additional actions could be
considered. Whereas some MPOs integrated a strong visioning process and/or
principles of strategic planning into their long range transportation planning
processes, many did not. Almost all MPOs included goals dealing with safety
and economic competitiveness, but few systematically considered these issues.
Most MPOs recognized the interaction between transportation and land use in
their policy statements, but alternative land use scenarios were rarely
considered. All MPOs identified goals, objectives and policies to guide their
long range transportation planning process, but the final list of cost feasible
projects was not always clearly linked to those goals, objectives and policies.
There was no statewide consistency in how needs and expected revenues were
identified, what the composition of these estimates should be or how this
financial information was reported. Several MPOs staged the implementation
of projects included in their cost feasible plan, but few identified a specific
mechanism for project programming in their long range transportation plan.
Specific observations included the following:
- In general, plan documents are better organized, more user friendly and
significantly more descriptive;
- Public involvement approaches improved dramatically throughout the
state;
- Only a few MPOs integrated a strong visioning process or strategic
planning principles into their long range transportation planning
process;
- The final list of cost feasible projects was not always clearly linked to
LRTP goals, objectives and policies;
- MPOs across the state employed various methods used to move projects
from need plans to cost feasible plans;
- There was a somewhat more balanced reliance on transportation
modeling and other considerations in plan development than was
observed in previous plan reviews; and
- A large shortfall between revenues and needs plan costs remains a
significant and widespread phenomenon.
Clear and significant improvements have been made in both the long range
transportation planning processes around the state and in individual plan
documents. The plan documents are better organized, easier to read and significantly more descriptive. Public involvement and regional coordination was
dramatically improved and the process is less reliant on modeling and includes
a wider range of planning considerations. While clearly improved, additional
enhancements could still be made. A series of suggestions are offered to enhance the effectiveness and clarity of future long range transportation planning in the state. In light of the improvements already made, MPOs will clearly continue to increase the value of Florida's regional long range transportation planning practices.
TABLE OF CONTENTS
INTRODUCTION
The Transportation Equity Act for the 21st Century (TEA-21) and its predecessor,
the Intermodal Surface Transportation Efficiency Act (ISTEA), strengthened local
and regional authority in transportation planning. Much of this new responsibility
fell to the Metropolitan Planning Organization (MPO), the federally designated
agency responsible for overseeing transportation planning activities in metropolitan
areas with populations of greater than 50,000 people.
Among other requirements, ISTEA and TEA-21 required MPOs to adopt long
range transportation plans (LRTPs) that:
- were based on a 20-year timeframe,
- were cost feasible based on reasonably expected revenue sources over the
life of the LRTP, and
- took into consideration several enumerated planning factors.
There was also an increased emphasis on involving the public in the decision-making
process, adherence to clean air standards, system preservation and increased
integration of transportation modes. In general, ISTEA and TEA-21 shifted the
focus of transportation planning away from narrowly addressing traffic congestion
through new highway construction to holistically resolving identified transportation
needs through enhanced multimodal transportation alternatives and improved long
range transportation decision-making.
However, while ISTEA and TEA-21 required the integration of several new
considerations in the long range transportation planning process, little additional
specific guidance was provided. The result has been a proliferation of approaches
to LRTP development across the nation and state.
1997 REVIEW OF LONG RANGE TRANSPORTATION PLANS
In 1997, the Metropolitan Planning Organization Advisory Council (MPOAC) asked
the Center for Urban Transportation Research (CUTR) to conduct a comparative
review of the LRTPs of Florida's twenty-five MPOs. The overall research focus was
to gain an understanding of the prevailing issues and challenges facing the different
urbanized areas of the state and to identify the methods in which MPOs chose to
address them.
Several notable issues were identified from the 1997 analysis of the twenty-five
MPO LRTPs. One major conclusion was that an abundance of plans were driven
by transportation modeling with limited consideration of other issues. No
standardized method for identifying and defining a future transportation need
existed and there was widespread uncertainty related to the identification of future
revenue, resulting in significant funding shortfalls around the state. The statewide
20-year funding shortfall, adjusted for varying base years and horizon years, was
estimated to be $22.3 billion expressed in 1995 dollars (26.3 billion in Year 2000
dollars).
MPOs displayed different degrees of concern and attention to environmental and
air quality issues. Many MPOs cited a general inability to interest the public in long
range transportation planning issues. They attributed that, in part, to a lack of
resources to undertake more ambitious public involvement efforts. There were
varying levels of intergovernmental and interregional coordination identified around
the state and a widespread lack of demonstrated systematic consideration of safety
issues.
Many MPOs integrated Florida Intrastate Highway System (FIHS) needs into their
LRTPs, but several found it difficult to address FIHS needs and local needs given
the general lack of resources. Several MPOs focused on the relationship between
transportation infrastructure development and economic competitiveness. Finally,
there was a pervasive "sanitization" of plan documents, offering little insight into
the transportation challenges faced in Florida's metropolitan areas and the manner
in which the state's MPOs collectively addressed those challenges.
Based on that review, the following suggestions for the next generation of long
range transportation plans were made:
- Incorporate discussion of current issues, a strong visioning process, and
principles of strategic planning into the long range transportation plans;
- Recognize the interaction between transportation and land use, with alternative
land use scenarios;
- Place greater emphasis on difficult policy trade-offs and less reliance on
transportation planning models;
- Standardize reporting of certain performance measures;
- Systematically assess safety considerations in plan development;
- Systematically consider hurricane evacuation in development of long range
transportation plans;
- Standardize the timing of plan updates throughout the metropolitan regions
and the reporting of estimated costs and projected revenues; and
- Report financial information by responsible agency and facility type.
2000 REVIEW OF NON-ATTAINMENT LONG RANGE TRANSPORTATION PLANS
As required by TEA-21, any MPO in a region that does not attain the standards set
forth by the federal Clean Air Act must update the LRTP every three years. Seven
of Florida's MPOs were in non-attainment areas including the Broward County
MPO, Hillsborough County MPO, Miami-Dade County MPO, Palm Beach County
MPO, Pasco County MPO, Pinellas County MPO, and Spring Hill/Hernando
County MPO. CUTR was again asked to review those seven updated MPO LRTPs
in 2000 to determine if there were any changes in the issues or challenges faced by
MPOs or the manner in which they address them. The plans were also reviewed to
determine if any of the MPOs followed through on the suggestions made following
the 1997 review.
In general, there were a number of improvements when comparing the 2000
updates to the 1997 LRTPs, while some of the same issues and challenges remained.
The 2000 review findings are listed below.
- In general, the plan updates included much richer descriptions of problems
and issues faced in the seven MPO areas. However, only a few MPOs
incorporated any visioning techniques into the plan development process.
More MPOs did incorporate strategic planning principles into their plan
development practices, but this was predominately limited to the testing of
widely different transportation alternatives.
- There was limited recognition of the interaction between transportation and
land use and no consideration of alternative land use scenarios.
- By and large the MPOs placed greater emphasis on difficult policy trade-offs
and while there was somewhat less reliance on transportation planning
models, the dominant factor driving project selection remained roadway
congestion as predicted by transportation models.
- The MPOs started reporting certain standard performance measures, but
few undertook a systematic assessment of safety considerations or systematically
considered hurricane evacuation.
- No significant steps were taken to standardize the timing of plan updates as
- TEA-21 requires non-attainment areas to update their LRTPs on a different
cycle than MPOs in attainment areas. While no effort was made to standardize
reporting of estimated costs and projected revenues, most of the
seven MPOs reported costs and revenues similarly because they generally
used the same source of information, the FDOT.
- The driving force behind cost estimates remained the manner in which
MPOs defined transportation needs. The standard modeling approach, in
which needs are identified based primarily on congestion relief, tends to lead
to a large number of needed highway widenings. In addition, MPOs tended
to meet their transit "needs" with premium transit services (express bus and
rail technologies). Premium transit services and highway widenings are
expensive and result in a very expensive list of needed transportation
projects.
As was found in the 1997 review, the combination of insufficient and uncertain
funding and broad definitions of transportation needs resulted in the
universal identification of funding shortfalls. The 20-year funding shortfall
for the seven LRTPs reviewed was estimated to be $14.3 billion, an increase
of approximately 30 percent over the 1997 funding shortfall estimate for
those same seven MPOs.
- MPOs started reporting financial information by responsible agency and
facility type.
- Public involvement efforts varied greatly among MPOs. A few MPOs did
not change their public involvement strategies (holding a few public meetings
and one public hearing during the middle of the day at a government
facility) from 1997 and the results (little attendance and low citizen input)
reflected that. Other MPOs dramatically improved their public involvement
strategies by increasing the frequency, timing and location of public meetings,
sending newsletters devoted to plan update issues to a wide audience,
developing interactive displays for placement at local activity centers, placing
relevant plan information on a dedicated web site and other such techniques.
These MPOs found that while it was still not a simple task to interest the
average citizen in long range transportation planning issues, public participation
and input did increase and issues that the community felt strongly about
were identified that might otherwise have gone unnoticed.
- Improvement was seen in addressing air quality issues.
2002 REVIEW OF LONG RANGE TRANSPORTATION PLANS
In 2002, CUTR was once again asked to conduct a comparative review of the
LRTPs of Florida's twenty-five MPOs. The timing was appropriate because each of
the twenty-five MPOs had completed at least a minor update of the LRTPs
originally reviewed in 1997. The scope of this review remained essentially the same
as earlier efforts. Particular attention was to be paid to the methods used to
establish project priorities, identify needs and move projects from needs plans to
cost feasible plans.
Several years had passed since ISTEA altered long range transportation planning
practice and TEA-21 had been adopted as the successor to ISTEA. The emphasis
on long range decision-making first established in ISTEA was continued in TEA-21.
While specific technical guidance remained limited, an effort was made in TEA-21
to streamline the long range planning focus by condensing the original sixteen
planning factors enumerated in ISTEA into these seven broad planning
considerations:
- Support the economic vitality of the metropolitan area, especially by enabling
global competitiveness, productivity, and efficiency;
- Increase the safety and security of the transportation system for motorized
and non-motorized users;
- Increase the accessibility and mobility options available to people and for
freight;
- Protect and enhance the environment, promote energy conservation, and
improve quality of life;
- Enhance the integration and connectivity of the transportation system,
across and between modes, for people and freight;
- Promote efficient system management and operation; and
- Emphasize the preservation of the existing transportation system.
Observations
In general, the quality of the most recent long range transportation plans improved
significantly compared to those reviewed in 1997 or 2000. Overall, plan documents
were more user-friendly and concise. They also contained less jargon and richer
descriptions of issues and challenges. There appeared to be a somewhat more
balanced reliance on modeling and a more obvious assessment of a wider range of
planning considerations than roadway level-of-service deficiency. There were
numerous examples of innovative public involvement efforts and improved regional
and interagency coordination. There was an increase in the consideration of
potential social and community impacts in the decision-making process and
thoughtful inclusion of community concerns into the decision-making process.
A variety of methods were used to select projects for the cost feasible plan with the
most popular approach being the use of a weighted prioritization formula. Almost
all the MPO plans incorporated the concepts of multimodalism and intermodalism,
including such alternative strategies as intelligent transportation systems (ITS),
corridor management, and transportation demand management (TDM). Even so,
financial shortfalls between the costs of identified needs and reasonably available
revenues remained a significant and widespread phenomenon. When added
together, the statewide 20-year shortfall estimate is $37.7 billion (in year 2000
dollars) -- a 43% increase over the 1997 statewide shortfall estimate.
Although the 2002 review identified numerous improvements in long range
transportation planning around the state, additional actions could be considered.
Whereas some MPOs integrated a strong visioning process and/or principles of
strategic planning into their long range transportation planning processes, many did
not. Almost all MPOs included goals dealing with safety and economic
competitiveness, but few systematically considered these issues. Most MPOs
recognized the interaction between transportation and land use in their policy
statements, but alternative land use scenarios were rarely considered. All MPOs
identified goals, objectives and policies to guide their long range transportation
planning process, but the final list of cost feasible projects was not always clearly
linked to those goals, objectives and policies. There was no statewide consistency in
how needs and expected revenues were identified, what the composition of these
estimates should be or how this financial information was reported. Several MPOs
staged the implementation of projects included in their cost feasible plan, but few
identified a specific mechanism for project programming in their long range
transportation plan.
The 2002 observations are based on reviews of long range transportation plans and
supplemental information gathered through interviews with MPO staff. In some
cases, additional plan documentation was incomplete or unavailable. Varying degrees
of information were provided from technical reports and summary documents.
A few MPOs chose to address particular subject areas in their short range
planning process, instead of their long range planning process. Therefore, while
this review of long range plans may indicate a lack of broad emphasis in a particular
subject area, MPOs may be addressing that issue in their broader transportation
planning practices.
Observations made during the 2002 review of Florida's twenty-five MPO long range
transportation plans are presented below.
In general, plan documents are better organized, more user friendly
and significantly more descriptive.
The majority of MPOs provide descriptive summaries of challenges and
solutions in place of the pages of transportation model output and spreadsheet
information that were prevalent in 1997. Many MPOs included userfriendly
charts, graphs, maps and other visual aids to enhance the readability
of the plan documents and make comprehension of the core material easier.
Also, several MPOs produced hard copy and electronic summary documents
highlighting the key information contained in the complete plan document,
making the information more accessible and easier to comprehend. Many
of these MPOs have made this information available on their web sites. A
few of these documents have taken unique forms, like the on-line "Cliff 's
Notes" version of the Hillsborough County MPO 2025 Plan and the pullout,
full-color poster of the Gainesville 2020 Plan.
The 1997 review of MPO plans concluded that plan documents around the
state were "sanitized." The implication of this finding was that the plan
documents at that time did not convey the challenges faced by MPOs during
the long range transportation planning process. The state's MPOs, by and
large, seem to have taken that observation to heart and have, in general,
made an effort to enhance the descriptive nature of their plan documents.
Policy rationales for decisions are often provided and obstacles and challenges
faced and overcome are widely discussed in plan documents. Examples
of this improvement range from a detailed description of the long
life cycle of a roadway project in the Polk TPO 2025 Plan to a detailed
explanation of local demographic issues and challenges in the Charlotte
County/Punta Gorda MPO 2025 Plan to a brief but informative explanation
in the Fort Walton Beach MPO Plan of why the MPO was not required to
conduct a major update of their previous LRTP and what it meant to
conduct only a minor update.
While there has generally been a dramatic improvement in the descriptive
nature of plan documents across the state, a few MPO plans replaced the
overly technical material of the past with all but the most basic information
and instead referred readers to technical reports numerous times in the plan
document without providing a description of the material contained in the
technical report. Although this practice does reduce the amount of material
in the plan document, it does not make it more descriptive. Readers are not
informed of concerns, issues, challenges, assessment approaches and other
decisions made during the long range transportation planning process.
Public involvement approaches improved dramatically throughout the
state.
Public involvement efforts throughout the state were more creative, more
varied and more effective than in previous long range plan development
processes. Public involvement techniques included such standard techniques
as public workshops, press releases and newsletters. More innovative techniques
used around the state included: focus group research in Pensacola, a
visual preference survey in Hillsborough County, simulation games in Charlotte
County, a regional survey in Orlando in cooperation with corporate
partners in the region, a random telephone poll in Hillsborough County, a
visioning charette in Gainesville, multi-lingual public information materials in
Miami-Dade County, area specific meetings in Tallahassee-Leon County,
television programming in Sarasota and Manatee Counties and traveling
displays and kiosks in Pinellas and Palm Beach Counties.
Also, there was an increased effort made to reach out to traditionally underrepresented
populations through targeted public involvement activities by
several MPOs around the state. The application of these varied public
involvement techniques resulted in higher levels of public participation than
has previously been the case.
Although the systematic consideration of safety was somewhat improved,
particularly related to hurricane evacuation, the practice was
still not widespread.
Almost all MPOs addressed the issue of safety as a broad goal in their long
range transportation plan, but only a few MPOs addressed issues of safety in
a systematic manner. Generally, MPOs that systematically considered issues
of safety did so through their prioritization process for selecting cost feasible
plan projects. Most MPOs used hurricane evacuation and/or crash
statistics as a criterion in their weighted prioritization formulas. Other
MPOs simply identified their highest crash locations or most congested
hurricane evacuation routes and included improvements to those facilities in
their list of cost feasible projects.
The Charlotte County-Punta Gorda MPO used a model developed by the
National Hurricane Center to estimate storm surge during hurricanes of
various intensities. This data was then matched against roadway characteristics
of hurricane evacuation routes (such as drainage conditions during
flooding and traffic volume during an evacuation) to determine which were
most likely to be significantly impacted during a hurricane. The results of
this comparison were then used to identify needed improvements to address
hurricane evacuation concerns.
The Polk TPO gave extra consideration to high crash locations by giving an
advantage in the prioritization process to candidate roadway projects with a
safety ratio of one or more. The safety ratio is a measure of how safe any
given roadway segment is versus other similar roadway segments in the state.
This ratio is calculated by dividing the actual crash rate (crashes per million
vehicle miles traveled) by the critical crash rate (the average crash rate of
similar roads throughout Florida).
-
Regional/interagency coordination has improved.
Plan documents from across the state reflected increased coordination with
neighboring MPOs and with other stakeholder agencies. The Fort Walton
Beach MPO sought out and received significant input from Eglin Air Force
Base. The Brevard County MPO coordinated with the plans of the
Kennedy Space Center and Florida Space Port. Several MPOs coordinated
their long range transportation planning effort with the long range planning
efforts of local universities.
In a few cases, formalized coordination occurred with neighboring MPOs.
The Treasure Coast MPOs (the Indian River County MPO, the Martin
County MPO and the St. Lucie County MPO) coordinated their individual
long range transportation planning activities. The West Central Florida
Regional Coordination Process covers the Tampa Bay area and includes the
Hillsborough County MPO, the Pinellas County MPO, the Pasco County
MPO, the Spring Hill/Hernando County MPO, the Polk TPO and the
Sarasota/Manatee MPO. These groups coordinated long range planning
activities and developed a regional planning strategy and goals. Additionally,
a single regional model (the Tampa Bay Regional Planning Model) covers the
four MPOs that comprise the single Tampa Bay Transportation Management
Area.
Further to the east, the Central Florida MPO Alliance is a formalized effort
to coordinate transportation planning activities between the Volusia County
MPO, the Brevard County MPO, METROPLAN ORLANDO and Lake
County (not yet included in an MPO area). This group has also coordinated
their efforts to pursue funding for large projects of regional significance and
establishes annual priorities as part of the program development process.
-
Almost all MPOs incorporated the concepts of intermodalism and
multi-modalism into their long range transportation plans.
Almost all MPOs planned for multi-modal improvements with intermodal
connectivity. For many MPOs, this was their first multi-modal long range
transportation plan. Improvements included in plans across the state ranged
from bike paths and sidewalks to multi-use trails, from light and heavy rail
lines to bus rapid transit and from HOV lanes to express bus routes. The
Hillsborough County MPO even developed a long range transportation
demand management (TDM) plan. The Tallahassee/Leon County MPO
conducted a two-tiered walkability/bikability analysis to target bicycle and
pedestrian enhancements to areas that have a high potential for bicycle and
pedestrian activity. Several MPOs now set aside flexible federal funds to be
used for transit and other non-highway projects to be selected as part of the
annual project prioritization process.
However, few MPOs considered non-highway alternatives in place of
highway capacity improvements. Rather, most MPOs considered nonhighway
improvements in addition to highway improvements. There were a
few notable exceptions in both large and small MPOs. One large MPO
example is the Broward County MPO. As matter of policy the Broward
County MPO Board sought to minimize roadway widenings and increase
transit service and connectivity in place of increased highway capacity.
Highway and transit alternatives were considered simultaneously during
alternatives testing. This approach resulted in significant spending on transit
improvements relative to highway improvements.
An example of a small MPO holistically considering highway and nonhighway
alternatives together is in Gainesville. The Gainesville MPO considered
all modal alternatives together in support of their land use vision. The
result was a project mix that included express bus service, new roadway
corridors to connect existing roadway corridors and a lane reduction with
enhanced pedestrian and bicycle facilities in yet another corridor. This
approach provided a blueprint for a future transportation system that meets
defined needs with an appropriate mix of modal facilities.
-
More consideration was given to social and community issues in the
long range transportation planning process.
Considerations around the state included the preservation of the natural
environment, the avoidance and mitigation of community impacts (cutthrough
traffic and division of a cohesive neighborhood, etc.), the level of
community support, and the potential impact to community aesthetics, and
cultural and historic resources. Additionally, several MPOs considered the
potential impact of projects, both individually and as a whole, on minority
and low-income populations. In some cases, projects were specifically
included in cost feasible plans in order to mitigate potential impacts as
identified through consideration of potential social and community impacts.
In other cases, projects were specifically excluded from cost feasible plans to
avoid creating new impacts or compounding existing ones.
The most common mechanism for considering potential social and community
impacts was to integrate them into the project prioritization process.
For example, the Panama City MPO considered the level of community
support as a qualitative factor for including candidate projects in the cost
feasible plan. The first screen of the Polk TPO three-tier screening process
was an assessment of potential significant negative impacts to the natural
and human environment.
Other MPOs took different approaches to considering potential social and
community impacts. The Miami-Dade County MPO established a Transportation
Aesthetics Review Committee that evaluated candidate projects. In
Panama City, projects were added to the cost feasible plan to address neighborhood
cut-through traffic issues and to provide community gateways. The
Spring Hill/Hernando County MPO mapped historic community locations
for further consideration in the planning process. The Pinellas County
MPO took into account municipal concerns over potential community
impacts, particularly in a few communities near the US 19 corridor where
roadway improvements were contemplated on parallel facilities that ran
through downtown commercial districts.
Several MPOs attempted to consider the potential environmental justice (EJ)
impacts of their plans. Most MPOs achieved this goal through the public
involvement process by reaching out to traditionally underrepresented
communities. Some also considered the potential EJ impacts of their plans
by identifying the geographic boundaries of established minority and lowincome
communities relative to the proposed location of candidate projects.
In some cases projects were identified for further review in later stages of
project development. In other cases, projects were modified or dropped in
order to mitigate potential EJ impacts.
-
Strong attention was paid by the MPOs to the seven broad TEA-21
planning considerations and to the identified needs of the Florida
Intrastate Highway System (FIHS), but little attention to the goals of
the 2020 Florida Transportation Plan (FTP).
Almost all MPOs enumerated the seven broad TEA-21 planning considerations
in their long range transportation plans. The Lee County, Spring
Hill/Hernando County and Hillsborough County MPO LRTPs each contained
tables assessing how their individual plan goals, objectives and policies
addressed the TEA-21 planning considerations. The Gainesville MPO
described how each project included in the cost feasible satisfied the TEA-
21 planning considerations.
The majority of MPO plans addressed the identified needs of the FIHS. In
some cases, FIHS projects were included in the cost feasible plan as a separate
project category and not included in the project prioritization process.
In other cases, FIHS improvements were given priority in the ranking
process, but not excluded from the process.
The 2020 FTP outlines the state's transportation goals and guiding principles.
While there is no requirement that MPO long range plans consider
the goals enumerated in the FTP, coordination between statewide and
regional transportation efforts would be desirable. Only two of the State's
twenty-five MPO long range transportation plans refer to the 2020 FTP.
The Indian River County MPO describes how their plan advanced the goals
of the 2020 FTP. The Volusia County MPO plan enumerates the FTP goals
and describes how their long range transportation plan is consistent with
those enumerated goals. However, many of the goals of the 2020 FTP are
advanced by the goals, objectives and policies of the LRTPs because of the
overlapping emphasis between the goals and guiding principles of the 2020
FTP and the planning considerations of TEA-21.
-
Only a few MPOs integrated a strong visioning process or strategic
planning principles into their long range transportation planning
process.
Visioning and strategic planning principles dictate the consideration of
"what if " scenarios and the assessment of a plan to meet those various
scenarios. Based on that definition, only a few of Florida's MPOs integrated
a strong visioning process or otherwise employed strategic planning principles
to guide the development of their long range transportation plan.
The most notable example of a long range plan based on a strong visioning
process is in Gainesville. The Gainesville MPO decided to abandon the
standard long range transportation planning process in which future travel
conditions are assessed based on the projected distribution of population
and employment according to future land use information contained in local
comprehensive plans. Instead, Gainesville undertook an extensive land use
visioning exercise in which four alternative land use scenarios were considered,
with considerable community input and involvement, and narrowed to
one land use vision for the region. Needs and Cost Feasible Plan projects
were then selected and tested in support of that land use vision. The result
is a plan driven by a vision of what the stakeholders of the region want their
community to look like in the future and strives to provide the necessary mix
of transportation facilities to support that vision.
The Tallahassee/Leon County MPO based their plan primarily on sub-area
visioning efforts they refer to as the Central City and Southern Strategies.
These strategies discourage continued growth to the north of the city center
and refocus development activities in the central and southern portions of
the metropolitan area. Policies have been developed to encourage this
desired development pattern. The MPO took this policy direction into
account when projecting and distributing future population and employment
in the long range transportation planning process. The result was the
refocusing of transportation infrastructure improvements in the LRTP to
those areas of the region.
A similar sub-area visioning effort guided the long range transportation
planning effort of the Polk County TPO. The TPO undertook an analysis
of four separate sub-areas of the metropolitan area in which alternate
population and employment forecasts were made. The separate area-specific
needs analyses led to the appropriate identification of transportation improvements
and strategies in those sub-areas. Additionally, corridor studies
were conducted in two of the sub-areas to examine improvement alternatives
for specific corridors.
Development of the Charlotte County/Punta Gorda MPO LRTP was
guided by the Charlotte County Vision. The Charlotte County Vision was a
collaborative visioning process conducted by Charlotte County, the City of
Punta Gorda and the MPO and included the consideration of four alternative
build-out scenarios. The MPO reported that the visioning effort resulted
in billions of dollars saved in road and bridge improvements, tremendous
reduction in emissions, and other public benefits.
The First Coast MPO strongly considered the goals and objectives of the
future vision for the Jacksonville metropolitan area as in the Better Jackson-
ville Plan. Several projects were included in the cost feasible plan to support
and advance Better Jacksonville Plan goals and objectives.
-
Although somewhat increased, there remains limited consideration of
alternative land use scenarios.
The overwhelming majority of MPOs take land use as a given and make
future population and employment distribution decisions based on the
information contained in local comprehensive plans. There are a few
exceptions. The Gainesville MPO, Tallahassee/Leon County MPO, Charlotte
County/Punta Gorda MPO and the Polk County TPO each considered
alternative land use scenarios based on visioning activities. In addition, the
Tallahassee/Leon County MPO integrated the findings of the Blueprint
2000 Plan, a comprehensive visioning exercise that was conducted by an
intergovernmental agency specifically created for the purpose of conducting
and implementing the Blueprint 2000 Plan.
An example of an MPO that considered alternative land use scenarios
outside of a visioning process is the Pensacola MPO. The Pensacola MPO
modified the distribution of future population away from Navarre Beach
and Southeast Escambia County toward Northwest Escambia County to
reflect a policy desire to shift future growth away from the coastline of
Escambia County. This significantly changed identified transportation needs
in the region and, in turn, yielded a final plan that included projects supportive
of the desired population distribution.
In another example, St. Lucie County and Martin County are currently
conducting a combined study of alternative future land use scenarios. The
results of this study may require reconsideration of the current MPO
LRTPs and will certainly influence the ongoing long range transportation
planning processes in both metropolitan areas.
-
Plan horizon years and timeframes are not standardized across the
state.
Of the 25 MPO LRTPs in Florida, 15 are 2025 plans while the remaining 10
are 2020 plans. This reflects more than the federally mandated update cycle
(every 3 years for non-attainment areas, every 5 years for the rest), as several
areas on the attainment area cycle completed 2025 plans covering a
timeframe of 25 years - 5 years longer than the standard LRTP. In addition,
MPOs with the same horizon year (2020 or 2025) do not always cover the
same time frame. Some MPOs have chosen to assess the timeframe between
plan adoption and the planning horizon year (2002 through 2025 for
example). Other MPOs chose to assume that the five-year time period
covered by the Transportation Improvement Program (TIP) did not need to
be accounted for in long range planning. These plans cover only the remaining
timeframe between the first year after the TIP timeframe and the
planning horizon year (2007 through 2025 for example). As a result, the 25
LRTPs in the state cover timeframes between 15 and 25 years, making
statewide comparisons of certain types of data (finances, population trends,
etc.) problematic.
One example of where this inconsistency in timing complicates statewide
comparisons is in population trends. Base year population projections in
MPO plans across the state range from year 1990 figures to year 2000, with
most falling in the middle. These base year population figures are then
projected to the horizon year of the plan, 2020 or 2025 depending on the
MPO. Because of the differences between the base years, the horizon years
and the timeframe being covered, direct comparison of these population
figures is complex, requiring a variety of assumptions to bring the figures
into alignment.
-
The reporting of financial data continues to be a complex exercise
that varies between MPOs.
MPOs across the state report financial data in disparate ways. MPO financial
data is expressed in a variety of base years, are projected to a variety of base
years and cover a variety of timeframes. Additionally, MPOs across the state
define the composition of financial data in a number of different ways.
For example, some MPOs calculate a needs plan and a cost feasible plan cost
for each mode (highway, transit, bicycle, pedestrian, etc.) at each level (state
and local) considered in the plan. Other MPOs only calculate needs plan
costs for some modes while calculating cost feasible plan costs for all modes
and present both as a total cost. A few MPOs did not distinguish between
operating costs and capital costs, particularly as they relate to transit, in
deriving a total plan cost. Still other MPOs simply report the expected
revenue for a given mode as the expected cost. A few MPOs used unit costs
to estimate project costs that differed from the unit costs used by other
MPOs. While these variations may make sense in the local context and make
the planning exercise more realistic, this lack of standardization makes
statewide comparisons of financial data problematic.
-
The final list of cost feasible projects was not always clearly linked to
the LRTP goals, objectives and policies.
Goals, objectives and polices (GOPs) are typically used to guide the long
range planning process and the final selection of cost feasible projects.
Collectively, GOPs appearing in plans around the state addressed a variety of
issue areas including: safety, congestion, capacity, environmental protection,
freight movement, multimodalism and intermodalism, economic vitality,
energy efficiency, system efficiency and preservation, system connectivity,
land development and growth, accessibility, mobility, coordination and more.
Several MPOs developed measures of effectiveness (MOEs) based on their
GOPs, presumably to measure the ability of projects to address plan goals.
Examples of MOEs included in plans across the state include: total miles of
transit service, percent of corridor miles served by transit, percent of
corridors with volume to capacity ratios of 1.0, percent of congested lane
miles, percent of corridor miles with bicycle lanes, total corridor miles with
sidewalks, hurricane evacuation route lane miles, lane miles with historic
significance, total crashes and fatalities, percent of congested roads with
sidewalks and more. Many MPO plans included long lists of GOPs and
associated MOEs.
However, there was not always a clearly documented link between the final
list of cost feasible projects and the original GOPs. Some LRTPs simply
state that the list of cost feasible projects support the GOPs, but provide no
supporting documentation to demonstrate this assertion. Several LRTPs
contain a detailed list of MOEs, but include no documentation of the ability
of final cost feasible plan projects to meet plan GOPs either through the
application of MOEs or through some other descriptive mechanism. Even
in some cases where a clearly defined mechanism was applied for the selection
of cost feasible plan projects, a clear link back to all or some of the plan
GOPs was not established. Two notable exceptions were the Panama City
and the Gainesville MPO plans. Each project included in these final cost
feasible plans was described in detail and an explanation of how each fulfilled
the goals of the plans was provided.
-
The definition of transportation need varied across the state.
Some MPOs defined a set of needed transportation projects strictly on
projected highway level of service deficiencies and projected transit ridership
demands. Other MPOs refined their definition of needed transportation
projects by considering policy, physical and environmental constraints,
effectively reducing the number of needed projects. Other MPOs, specifically
excluded projects considered to be unrealistic, too controversial or
overkill. For example, the Miami-Dade County MPO excluded what they
referred to as "gold plated" transportation options where cheaper alternatives
could be identified that still met the projected demand. The Panama
City MPO plan also specifically stated that unrealistic projects were excluded
from inclusion in the needs plan. The Gainesville MPO revised its land use
vision to, in part, generate a more realistic set of needs plan projects. Another
factor directly impacting the determination of transportation needs is
the population projection in the metropolitan area. Higher population
growth rates tend to lead to an increase in the projected travel demand,
often resulting in more needed projects.
Therefore, MPOs that anticipated significantly larger population growth
than other similarly sized MPOs tended to identify more transportation
needs. As a result of these policy decisions and factors, MPOs of comparable
size reported dramatically different shortfalls between their needs plan
costs and reasonably available revenue, with some shortfalls being very large
and others being relatively modest in size.
-
MPOs across the state employed various methods to move projects
from needs plans to cost feasible plans.
The methods used for selecting projects included in the cost feasible plan
generally fell in one of three categories: the subjective policy driven approach,
the deficiency assessment approach and the prioritization formula
approach. The Miami-Dade County MPO used a subjective ranking approach
in which all needs plan projects were assigned a score of between -
10 and +10 based on their perceived ability to advance plan goals and
objectives. The list of cost-feasible projects was based on that ranking, with
some minor common sense modifications. The Panama City MPO also
employed a subjective review of needs plan projects based on a variety of
criteria. A few MPOs simply performed a level-of-service deficiency analysis
using the standard transportation model and selected projects based on their
ability to relieve future congestion.
The most popular approach was the use of weighted prioritization formulas.
This approach assigns overall scores to each project included in the needs
plan based on the project's ability to satisfy a set of individual quantitative
and/or qualitative criteria. Each candidate project is assigned a score for
each individual criterion. Then an overall project score is tabulated based on
a formula that is generally weighted to reflect a given policy emphasis.
Projects are then ranked by their total score and included in the cost feasible
plan as projected revenues permit. A few MPOs use formulas with different
criteria depending on the mode of the projects being considered. For
example, the Hillsborough County MPO employed 10 criteria in a weighted
formula used to prioritize highway projects, 9 different criteria in a weighted
formula to prioritize bicycle and trail projects, another 4 criteria in the
sidewalk formula and yet another 5 criteria in the transit formula.
One of the most extensive prioritization methodologies was found in the
Polk TPO LRTP. The Polk TPO employed a three-tier analysis of candidate
projects. The first tier was a fatal flaw analysis in which projects with the
potential to create significant negative environmental or community impacts
were eliminated from the candidate project list. Those projects that passed
the tier 1 screening were then evaluated under tier 2 and 3. The second tier
gave weight to projects that were needed in the short-term, projects that
were candidates for later phases of the project development cycle, and
projects that contributed to system preservation. The third tier assessed
projects relative to TEA-21 planning considerations. The specific criteria
assigned points relative to a candidate project's perceived ability to relieve
traffic congestion, improve freight/goods movement and economic competitiveness,
improve community livability and not negatively impact neighborhoods
and businesses, avoid impacts to the natural environment and
address safety concerns.
-
There was a somewhat more balanced reliance on transportation
modeling and other considerations in plan development than was
observed in previous plan reviews.
Historically, identifying future roadway level-of-service (LOS) deficiencies
and future roadway projects to improve those deficiencies has been the
primary focus of long range transportation planning in Florida. These
planning processes relied heavily and sometimes exclusively on the output of
transportation models. Long range transportation plans were filled with
model output and large portions of the plan were dedicated to descriptions
of the modeling effort. ISTEA followed by TEA-21, shifted that focus on
future roadway LOS deficiency to a variety of other factors as outlined in
the seven TEA-21 planning considerations.
As demonstrated by the long list of goals, objectives and policies in the
State's current MPO plans, and the variety of prioritization methods and
criteria employed, it is clear that MPOs are considering a number of factors
in developing their long range transportation plans. While transportation
modeling is still clearly an important tool in the long range transportation
planning process, it no longer appears to be the primary driving force in the
process in most cases. However, there were still a few examples where the
roadway LOS deficiency analysis based on transportation model output
remained the overwhelming force behind cost feasible project selection.
-
Detailed consideration of economic competitiveness and/or freight
movement was not widespread.
While most MPOs included the issue of economic competitiveness and/or
freight and goods movement in plan goals and objectives, only a few MPOs
considered these issues in any detailed or systematic fashion during plan
development. The majority of MPOs that did consider these issues in a
more concrete fashion typically did so through their project prioritization
process. A few MPOs established freight and goods movement advisory
boards.
The Miami-Dade County MPO included projects in their cost feasible plan
for the explicit purpose of improving freight movement to enhance economic
competitiveness. An under-bay tunnel project was included in the
cost feasible plan to enhance access to the Port of Miami. Extensive surface
street improvements were also included in the cost feasible plan to enhance
circulation in the Cargo City area, the intense cargo handling area near the
Miami International Airport. The Brevard County MPO took into consideration
the freight movement needs of the Kennedy Space Center and Florida
Space Port.
The Spring Hill/Hernando County MPO identified and mapped routes with
heavy truck traffic, intermodal facility locations and freight movement in the
county. Indian River County also identified and mapped intermodal facility
locations and roadways that serve those facilities as well as heavy truck traffic
roadways. This information was used to focus plan development in an
effort to meet freight and goods movement needs in both MPO areas.
-
Corridor management and preservation was considered by a few
MPOs in the development of their long range transportation plan.
A few MPOs addressed the issue of corridor management and preservation.
The St. Lucie County MPO identified corridor preservation as one of the
criteria used to prioritize needs plan projects for inclusion in the cost feasible
plan. The Martin County MPO included a map identifying the right-of-way
requirements of the long range transportation plan. The map identifies
generalized roadway requirements, the future maximum number of through
lanes, the roadway functional classification and constrained facilities. The
Hillsborough County MPO plan included a plan objective to support the
adoption of local right-of-way preservation policies and ordinances and
included the preservation of land for future transportation needs as a
prioritization criterion for evaluating candidate projects. The Spring Hill/
Hernando County MPO plan also included a plan objective that encouraged
the preservation of right-of-way sufficient to accommodate roadway, transit
and other transportation modes.
The three Panhandle MPOs identified corridor management as an important
element for the implementation of their plans. In February 2002, one-day
corridor management workshops were held in each of the three MPO areas.
The workshops, targeted at local planning, engineering and legal staff,
focused on corridor management benefits, strategies and legal underpinnings.
A brief overview presentation on corridor management was also
provided for each of the three MPO Boards.
-
There was an increase in the application of Intelligent Transportation
Systems (ITS) technology.
Several MPOs considered ITS in their long range planning efforts. A few
MPOs, including METROPLAN ORLANDO and the Pinellas County
MPO, established ITS subcommittees to ensure the consideration of ITS in
the long range transportation planning process.
One of the most popular ITS applications around the state was the installation
of a computerized signal system. This will enhance operations on the
existing transportation network and improve both system efficiency and
safety. The Miami-Dade County MPO designated twelve priority ITS
corridors in the metropolitan area. A variety of ITS treatments will be used
in those corridors to ease congestion. The ITS projects are in place of
wide-scale capacity projects.
The Pasco County MPO has committed to set aside $1 million per year to
fund future ITS projects in the County and has also committed to ITS
improvements in the US 19 corridor. The First Coast MPO also set aside an
annual allocation of funds for use on ITS projects to be selected during the
annual project programming process.
The Lee County MPO has committed to several ITS projects in the County
and is currently developing an ITS plan that will then be integrated into the
current long range transportation plan. They are also studying an incident
management system for the bridges over the Caloosahatchee River bridges.
The Pinellas County MPO describes a three-phase ITS improvement strategy
in the long range transportation plan. The first phase focuses on northsouth
routes in the County. The second phase focuses on east-west routes
and the third phase focuses on other priority corridors.
-
Few MPOs defined a specific mechanism for project programming in
the long range transportation plan.
Several MPOs did identify a time frame for project implementation through
the staging of their cost feasible plans into short-range (interim) and long
range components. Staged plans were typically broken into two or three
stages covering relatively equal time frames within the broader time frame of
the overall plan document. In a few cases, the first stage included only
projects that were already programmed in the then current Transportation
Improvement Program (TIP). MPOs that staged their cost feasible plan
indicated that they use the staging as a guide for prioritizing projects during
the annual project programming process.
The Martin County MPO identified specific criteria for annually prioritizing
cost feasible plan projects for inclusion in the TIP. The ranking assigned to
candidate projects in the Gainesville MPO Needs Plan is maintained for
programming purposes. Therefore, the number one ranked candidate
project was included at the top of the cost feasible plan list of projects and
is in line for funding ahead of any other cost feasible plan project.
-
A large shortfall between revenues and needs plan costs remains a
significant and widespread phenomenon, leading to a statewide 20-
year shortfall estimate of $37.7 billion in Year 2000 dollars (a 43%
increase over the statewide shortfall estimate from 1997).
Taking into consideration the issues related to the reporting of financial data
and the identification of needed transportation improvements, it remains
obvious that each MPO finds itself with too little revenue to meet anticipated
needs within the timeframe of their individual long range transportation
plan.
Shortfalls for individual MPOs ranged from as low as $86.3 million to as
high as $5.62 billion in Year 2000 dollars. Interestingly, the size of the
individual metropolitan area was not always a determinant of the size of the
shortfall, as some smaller MPOs reported larger financial shortfalls than
MPOs in larger metropolitan areas. The statewide 20-year shortfall, expressed
in year 2000 dollars, was estimated to be $37.7 billion. This is 43%
greater than the $26.3 billion dollar shortfall estimated in 1997 (as expressed
in Year 2000 dollars).
This statewide shortfall estimate was calculated using information from each
individual MPO plan, supplemented by information provided by MPO staff.
Some adjustments were necessary to methodically compare the financial
information and arrive at a cumulative, statewide financial shortfall estimate.
All financial data was adjusted to reflect year 2000 dollars. In order to
account for differing plan horizon years (2020 and 2025) and different time
periods covered by individual MPO plans (ranging between 15 and 25 years),
an average annual shortfall estimate was calculated by dividing the total
financial shortfall by the number of years covered by the plan. The cumulative
average annual plan shortfall estimates were then multiplied by 20 to
arrive at a statewide 20-year shortfall estimate, expressed in year 2000 dollars.
As has been previously noted, the composition of needs plan costs varied
around the state. Some MPOs included operating costs in their total needs
plan cost estimate. Some MPOs included highway, transit and other nonmotorized
project costs in their total needs plan cost estimate while others
only included highway project costs. Other MPOs included some alternative
combination of project costs. It was not always clear from the information
available how various project categories contributed to the overall shortfall.
Suggestions
Based on the 2002 MPO LRTP review observations, the suggestions below are
offered to improve the effectiveness and clarity of future LRTP updates.
Where possible, provide informative descriptions of issues faced,
challenges overcome and policy decisions made in clear and simple
language within the plan document.
An over-reliance on references to information contained in technical reports
and appendices can obscure the core information provided in the primary
document. Reducing such references and improving descriptions in the
primary text will enhance the quality of the long range transportation
planning process.
-
Incorporate a strong visioning process and principles of strategic
planning into the long range transportation planning process.
The result will be a planning process that is grounded in a consensus view of
what the community should look like in the future, identifies challenges
faced in achieving that vision and fosters the development of strategies for
addressing those challenges.
-
Recognize the interaction between transportation and land use by
considering alternative land use scenarios.
This could be accomplished through a visioning process or other means.
Whatever the approach, considering alternative land use scenarios would
result in a more appropriate mix of planned transportation facilities and
help bring the local land use planning process and transportation planning
process into balance.
Clearly link the final list of cost feasible plan projects to plan goals,
objectives, and policies.
This can be done through the application of measures of effectiveness,
through project descriptions, or through a variety of other mechanisms.
Linking cost feasible projects back to the original goals clearly documents
the consistency of the decision-making process and strengthens the credibility
of the process.
Integrate consideration of potential social and community impacts
into the long range transportation planning process.
Consideration of potential social and community impacts will streamline the
project development process for each individual project contained in the
cost feasible plan and improve public acceptance of the plan in general.
Cooperatively develop guidelines for determining needed projects.
While every MPO should decide its own individual needs, the definition of
need varies dramatically across the state. A few needs plans around the state
appeared to include premium transportation options where a less expensive
or less controversial option would have satisfied the defined transportation
need. This inflates the reported cost of transportation needs in that MPO
area and may reduce the credibility of the planning effort in the eyes of
federal and state officials, as well as the general public. Developing and
applying consistent guidelines for defining transportation needs would
provide a more realistic assessment of actual needed transportation improvements
and help normalize financial shortfall estimates around the state.
-
Where appropriate, consider non-highway improvements in place of,
rather than in addition to, highway improvements.
Wherever feasible, MPOs should consider non-highway alternatives to meet
identified transportation needs and other policy goals. This should include
not only transit, bicycle and pedestrian facilities, but also intelligent transportation
systems technology and transportation demand management strategies.
The result will be a truly multi-modal long range transportation plan
that meets the mobility needs of the metropolitan area with the appropriate
transportation mode under the appropriate circumstances.
Select cost feasible plan projects from among candidate projects using
a systematic methodology that addresses a variety of policy concerns.
This will result in a project selection process that balances a variety of
community concerns in a clear and defendable manner and enhances the
ability of the responsible transportation agency to effectively implement the
project. It will also reduce the over reliance on transportation modeling in
the long range transportation planning process.
Cooperatively develop guidelines for reporting financial data.
The guidelines should cover the composition of revenues and costs, the
timeframe to be covered by the financial data and the base year. Currently,
the financial data contained in the state's MPO LRTPs varies from plan to
plan. Different timeframes are covered, the composition of costs and
revenues change from MPO to MPO and base years are inconsistent. Consistency
in the reporting of financial data would make accurate statewide
comparisons possible and enhance the ability of the MPOAC and FDOT to
help MPOs meet the transportation needs of their regions and in turn the
state as a whole.
Whenever possible and appropriate, coordinate planning activities
with neighboring MPOs and stakeholder organizations.
This will result in improved transportation connections across county and
regional lines. Also, involvement of stakeholder agencies will leverage their
individual planning efforts and streamline the project development process
by removing potential conflicts of interest and informing permitting agencies
of potential projects very early in the process.
Take into account future right-of-way needs of planned transportation
improvements through the advancement of corridor preservation
strategies and concepts.
Identifying generalized future transportation right-of-way needs would
provide a starting point for corridor preservation activities in a metropolitan
area. Those activities may range from opportunistic advance acquisition
activities to negotiated right-of-way dedication through the land development
process.
Define a specific mechanism or strategy for programming projects
included in the cost feasible plan.
The establishment of a specific mechanism or strategy for funding cost
feasible plan projects will streamline and simplify the annual programming
process. It will also establish a stronger tie between long range transportation
planning at the systems level and project planning at the individual
project level by creating a transparent link between the two.
SUMMARY
Clear and significant improvements have been made in the long range transportation
planning processes around the state and in individual plan documents. The plan
documents are better organized, easier to read and significantly more descriptive.
Public involvement and regional coordination is dramatically improved and the
process is less reliant on modeling and includes a wider range of planning considerations.
While clearly improved, additional enhancements could still be made. A
series of suggestions are offered to enhance the effectiveness and clarity of future
long range transportation planning in the state. In light of the improvements
already made, MPOs will clearly continue to increase the value of Florida's regional
long range transportation planning practices.
|